
Repair of the main cable at Utgrunden Wind Turbine Farm
The client: Energi E2
The place: Öland, Sweden
|
|
|
|
Excavator |
Cable-snit |
Jack-up platform Explorer |
Cable trench |
The work: In June and July 2006
JD-Contractor A/S exchanged and embedded the main cable from the
shore and approx. 2 kilometres out to the Utgrunden Wind Turbine
Farm in Sweden.
Earlier in 2004 and 2005 JD-Contractor A/S had
made a successful exchange of all the submarine cables between the
7 offshore wind turbines at Utgrunden Wind Turbine Farm.
The seabed close to the beach at Degerhamn exists
of extremely hard materials, which meant that the cables had to
be laid in excavated trenches, which involved the use of 2 excavating
vessels.
The following vessels were used during
the work:
M/S Honte:
1. Laying of the new submarine cable.
2. Moving the existing cable into the bottom of the trench.
M/V Lille Björn:
1. Assistance for M/S Honte and towing of the jack-up platform.
2. Transport of cable jointers, personnel and equipment.
Stf. Helle Saj:
1. Excavating of the trenches for the cables at a depth from 2.5
to 10 metres.
2. Covering of the cables at a depth from 0 to 2.5 metres into the
seabed.
Jack-up platform Explorer:
1. The cable jointers used the Jack-up platform for cable splicing
at sea.
Excavating vessel from Per Aarsleff:
1. Excavating of the trenches for the cables at a depth from 0 to
2.5 metres into the seabed.
2. Covering of the cables at a depth from 0 to 2.5 metres into the
seabed.
Furthermore a diving team assisted during the entire
work. At first they marked the existing cable with buoys from the
shore and out. Then later they inspected and approved the excavating
and covering of the trenches.
Approx. 800 metres of existing cable were recovered
and replaced by a new cable.
Approx. 2,000 metres of trenches were excavated
into the seabed where the existing and the new cable were moved
into.
|