Laying and embedding of a cable pipeline from Jutland to the Isle
of Fur
The client: Energi Midt A/S
The place: Fursund, Denmark
The work: JD-Contractor A/S laid
out and embedded a cable pipeline between Jutland and Fur in mid-July
2006. A floating stage and the diving vessel M/S Honte were used
during the work in Fursund.
The work was split up into the following stages:
1. M/V Buizerd carried out a preliminary survey of the seabed in
Fursund at the beginning of March 2006.
2. Welding, laying and ballasting of the pipeline.
3. Excavation of trenches close to shore.
4. Embedding of the pipeline into the seabed.
The pipeline was delivered in coils of 100 metres.
It was then loaded, welded together and ballasted onboard the floating
stage, assisted by the diving vessel M/S Honte. When the loading
was finished and an excavator had excavated the two trenches from
each shore, the diving vessel M/S Honte embedded the pipeline into
the seabed.
Approx. 80 metres of trenches were excavated into
the seabed from the shore in Jutland and approx. 100 metres of trenches
were excavated into the seabed from the shore on Fur.
Approx. 965 metres of pipeline were laid out, ballasted
and embedded at a depth of min. 1 metre into the seabed.
The work, including the preliminary survey, lasted
5 days and was carried out as scheduled. |