Cable repair between Rødvig and Rønne
The client: TDC
The work: From January 2005 to
February 2006 the cable laying vessel C/S Cable One repaired and
embedded a cable between Rødvig and Rønne. C/S Cable
One carried out a survey of the seabed near the cable in order to
determine the position of the damaged part, of the cable. After
the location of the damaged part the cable was repaired and embedded
into the seabed.
Approx. 200 metres of existing cables were recovered,
approx. 350 metres of cables were laid and approx. 750 metres of
cables were embedded into the seabed.

|