From 22nd of August 2005 to 29th of September 2005 JD-Contractor A/S delivered, layed out and embedded a pipeline under Holbæk
Fiord in connection with the cutting off of Markeslev purifying
plant.
JD-Contractor A/S, a specialist in cable- and pipeline
work, carried out the following tasks:
Preliminary survey of the seabed.
Mobilization and establishment of working places.
Excavating of trenches at landings and areas with rough seabed.
Welding of the pipeline.
Ballasting and laying of the pipeline.
Embedding of the pipeline into the seabed.
Covering of the pipeline.
Pressure test of the pipeline.
Demobilization and re-establishment of working places.
The following vessels were used during the work at Holbæk
Fiord:
M/S Honte
1. Laying of the pipeline.
2. Control of trenches and embedding of the pipeline.
T/B Lille Bjørn
1. Assistance for M/S Honte during the laying and embedding of the
pipeline.
M/V Helle Saj
1. Excavating of trenches for the pipeline.
2. Covering of the pipeline.
The work was carried out as scheduled and by the
end of the last working day JD-Contractor A/S was a week ahead of
schedule.
Approx. 2,800 metres of trenches were excavated
and approx. 2,800 metres of pipelines were laid out and embedded
into the seabed. |