Home
   
Profile
Services
   
Diving
Fleet
Equipment
References
Videos
Contacts
News
  - 2010
  - 2009
  - 2008
  - 2007
- 2005 and 2006
- 2004 and previous
  - Other projects
Links
   
D4 InfoNet

 

Laying and embedding of pipeline under Holbæk Fiord

 

Client: Holbæk Forsyning
Place: Denmark
 

 

From 22nd of August 2005 to 29th of September 2005 JD-Contractor A/S delivered, layed out and embedded a pipeline under Holbæk Fiord in connection with the cutting off of Markeslev purifying plant.

JD-Contractor A/S, a specialist in cable- and pipeline work, carried out the following tasks:

Preliminary survey of the seabed.
Mobilization and establishment of working places.
Excavating of trenches at landings and areas with rough seabed.
Welding of the pipeline.
Ballasting and laying of the pipeline.
Embedding of the pipeline into the seabed.
Covering of the pipeline.
Pressure test of the pipeline.
Demobilization and re-establishment of working places.

The following vessels were used during the work at Holbæk Fiord:

M/S Honte
1. Laying of the pipeline.
2. Control of trenches and embedding of the pipeline.

T/B Lille Bjørn
1. Assistance for M/S Honte during the laying and embedding of the pipeline.

M/V Helle Saj
1. Excavating of trenches for the pipeline.
2. Covering of the pipeline.

The work was carried out as scheduled and by the end of the last working day JD-Contractor A/S was a week ahead of schedule.

Approx. 2,800 metres of trenches were excavated and approx. 2,800 metres of pipelines were laid out and embedded into the seabed.

 

Prev page Next page

JD-Contractor A/S Nybovej 8-9 7500 Holstebro Tel. (+45) 9742 6311 post@jdcon.com