By following the anchor trace, the fault in the cable was localised. Divers then mounted lifting straps and fitted taifun wire so both cable ends were ready for lifting. Due to the risk of water damage between joints 33 and 34, the whole length of cable approx 2.4 km between the two was retrieved. When the weather improved 2.5 km of new cable was severed, made water tight and layed. After the cable was laid, M/S Marcos was used as a platform for splicing the cable ends supported by the tug T/B Naja. Bad weather delayed the start of the repair, but the splicing of the cables was completed in only 3.5 days.
Related links:2009 – Seven repairs to Subsea Cables: click here 2008 – Kontek repairs: click here 2007 - Cable damage at Sejerø quickly repaired: click here 2007 - Cargo ship damages six submarine cables: click here 2006 - Repair of the main cable at Utgrunden: click here 2006 - Reparation of the Kontiskan cable: click here 2006 - Reparation of the Kontek cable: click here 2006 - Cable repair between Rødvig and Rønne: click here 2005 - Cable repair between Bornholm and Sweden: click here 2005 - Blackout on Femø: click here 2004 - Blackout on Bornholm: click here
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
JD-Contractor A/S |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||