Client: Frederikshavn Elnet A/S
Date: 29. July - 14. August 2009
JD-Contractor A/S was contracted to lay and bury a new 12 kW power
supply cable in the shallow passage between Frederikshavn and Hirsholmene.
Prior to the work, JD-Contractor A/S did a thorough survey of the
area: Jetted samples of the seabed were analysed and divers investigated
the entire area. As a result of our measurements and observations,
Frederikshavn Elnet A/S agreed upon the final positioning of the
cable as shown in the above picture.
The cable was delivered in 5 sections and spliced into 2 longer
lengths on land. They were then loaded onto the multi-purpose barge
S/B Victor and unloaded from the harbours at Rønne and Hirsholm
respectively. A final splicing was done on board S/B Victor after
the two cables were unloaded, and the entire cable was then laid
on the seabed.
The seabed at Hirsholm is very stony so before the cable could
be laid a pre-dug trench was prepared for the cable to be placed
in. The rest of the area was smooth, so the cable was laid on the
seabed by JD-Contractor A/S’ jetting unit ”LIGHT-JET
10”
6 km of cable were laid and buried.
725 m were buried into the seabed and 5275 m was jetted down into
the seabed.
The following vessels were used for the assignment:
T/B Naja: tugboat
M/S Honte: diving support and jetting equipment
S/B Victor: cable laying and dispersion of gravel to cover the laid
cables
|