32 kV Cable repair between
Vestmanna and mainland of Iceland:
Client: Landsnet in Iceland
July - August 2008
In a close race with time and the harsh weather
conditions in the waters around Iceland, JD-Contractor A/S assisted
NKT in a cable repair at Vestmanna Island.
This was done in close connection with the laying
of a freshwater pipe in the same area, from our vessel C/B Henry
P. Lading.
Earlier inspections had shown some severe deterioration
of the cable. It was therefore decided to replace part of the
old cable.
During the operation it turned out that the armor
over long distances was totally corroded away so in all 840 meters
were replaced.
Due to very short periods with suitable weather,
the work had to be performed in stages as the weather allowed
for it. Nonetheless, the work was carried out within the time
calculated for the project.