Laying and Embedding of Cable
bundle at Guldborgsund, Denmark.
Client: SEAS-NVE
From 9th to 20th June 2008 JD-Contractor A/S
laid and embedded seven cables and pipes in one bundle over a
distance of 1438 m at Guldborgsund between Lolland and Falster.
Until now, this has been the most we have laid. The challenge
was handling this number of units together and laying them without
damaging any of them.
The cables and pipes were delivered in their full length on reels
and loaded onto the multi purpose barge S/B Victor. A total load
of about 100 metric tons.
The cable was for most of the distance laid in pre-excavated trenches;
the rest was laid on the seabed and later jetted down.
The cable bundle consisted of 7 cables.
Total weight: 64 kg per meter.