When the cables had
been successfully recovered in the area, a trench with the depth
of 3 metres and the width of 10 metres was excavated into the seabed.
The excavating work was carried out by the two excavating vessels
M/E Helle Saj and M/E Nicolaj Saj. In the meantime the two pipeline
systems were welded together ashore. Parallel with the establishment
and ballasting of the pipeline systems, they were pulled out in
Masnedsund by M/S Honte.
As both pipeline systems were pulled out from ashore,
M/V Lille Björn towed them, so they were in the cable trace
and in a straight line parallel with the Masnedsund Bridge. The
pipeline systems, which were air filled, were then filled with water
in order to lower them down into the excavated trench. After the
laying and the lowering of both pipeline systems were finished,
the trench was covered up with the materials from the excavating.
A total of approx. 264 metres of trenches were
excavated and as a result approx. 7,000 m3 of materials were removed
in the area in Masnedsund. Afterwards approx. 2 x 264 metres of
cable pipelines were laid out and the materials were put back into
the trench.
The establishment of cable pipelines in Masnedsund
was finished on the 11 October 2007. When finished, both of the
pipeline systems were video filmed and approved by a diving team,
before the floating stage and working place ashore were demobilized.
M/S Honte and M/V Lille Björn departured from Vordingborg port
on the 13 October 2007.
JD-Contractor A/S was responsible for the delivery
of all materials for the project, as well as the welding, ballasting
and establishment of the two pipeline systems.
For the work at Masnedsund the following vessels were used:
• The diving
ship M/S Honte,
• the multi-working vessel M/V
Lille Bjørn,
• the excavating vessels M/E Helle
Saj and M/E Nicolaj Saj,
• the tugboat T/B Rita Saj with
barge,
• four rubber boats
• and finally our floating stage.
|