The pictures
above are from the transport and laying of 21 km
of power cable to 7 islands in Thailand. All the
cables were trenched as a post operation, from a
local barge, by JD-Contractor A/S
|
|
Laying out cables with the coaster system
The coaster system is another system
to load, transport and lay mainly power cables from a chartered
cargo ship.
The system consists of a coil tank, a coil wheel,
some roller paths, a linear machine and a cable chute. After the
cable is laid out, the system is dismantled and shipped back in
containers and the ship is delivered back to its owner.
|